Progress from our live sites, new project announcements, and the teams delivering the work. For our charity, apprenticeship and community work, see Social Value.
Power Hall
Reopens After
Four Years
The Power Hall at the Science and Industry Museum has reopened as The Andrew Law Gallery following a four year restoration, and is now shortlisted in two categories at the Museums and Heritage Awards.
Our team stripped the roof of the Grade II listed former railway shed to carry out extensive repairs to the original timber trusses, then rebuilt it with new timber sub-frames and woodfibre insulation. Most of the original slates were reused. The work forms part of a decarbonisation programme cutting the museum emissions by 515 tonnes of carbon dioxide a year.
Looking Back At The Power Hall
A return visit to the Andrew Law Gallery at the Science and Industry Museum, now open to the public after a four year restoration.
Library
Restoration Begins At Northwich Library
Original glazing removed for overhaul, with leaded glass reinstated in place of the modern panes fitted during an earlier refurbishment.
Northwich
New Project: Northwich Library
Appointed by Cheshire West and Chester Council. Timber frame repairs, all roofs stripped and reinstated, energy efficiency upgrades and a new platform lift. Completing 2027.
Cottages
Brickwork
Glasshouse Foundations At Bothy Cottages
An important milestone at Haigh Hall as the foundations for the new glasshouse take shape. For Wigan Council with support from The National Lottery Heritage Fund.
Blackburn
RAAC Removal Progresses At Royal Blackburn
Temporary roof erected, internal strip out complete, and the RAAC panels now being removed at roof level with steel installed to support the new timber truss roof.
With The
Team
On Site With Adam And Padraig
Two of our site team talk through progress at Royal Blackburn Teaching Hospital and Earlestown Town Hall.
Tottington
Ferns Farm Takes Shape
Foundations and blockwork complete on a new build home in Tottington, with aerial footage showing the house begin to sit within its setting.
Town Hall
Milestone At Earlestown Town Hall
First fix MEP complete as the project moves into the finishing trades, with heritage plaster works and second fix joinery now under way.
Touchstones Approaches Handover
Retractable bleacher seating installed and the Crittall style doors and screens complete as the project nears its final clean and handover.
Chapel
Milnrow Chapel Reimagined
A 1960s chapel at Hopwood Hall College becomes a modern learning space while its concrete structure and colourful lantern are preserved.
Rylands
Roof Repairs Under Way At John Rylands
Scaffold fully erected and the watertight structure complete, with temporary protection installed to the Spinningfields elevation ahead of asphalt repairs.
Cottages
Bothy Cottages Update
Aerial footage over Haigh Hall shows the scale of the restoration bringing the estate historic working buildings and yard back into use.
Extension
Café Extension Watertight At Earlestown
With the extension fully watertight, first fix MEP is complete and tanking, insulation and screeding have commenced on the ground floor.
Roof
Complete
Lantern Roof Complete At Milnrow Chapel
The first full restoration of the upper roof since the lantern was built in the early 1960s, marked with a ceremony attended by the College Principal and Seven Architecture.
Royal
Blackburn
New Project: Royal Blackburn Teaching Hospital
A complex refurbishment of the Tower View Building as part of the RAAC removal programme, delivered within a live hospital environment.